Submission incomplete:
1.The DOE is requested to upload the respective modalities of communication (MoC) to the project view page as requested by paragraphs 8 (e) and 10 (d) of EB 48 Annex 60.
The DOE and Project Participants are kindly requested to use the approved "Modalities of Communication" avoiding modifications to the document itself (e.g. copy and paste of sections of "primary signatory")
2.The DOE is requested to upload a valid letter of approval/authorization (LoA) from the host party to the project view page as requested by paragraphs 8 (c) and (d) and 10 (c) of EB 48 Annex 60.
This is only a request for future submissions: The DOE and Project Participants are kindly requested to provide Letter of Approvals which fully display the project title of the project activity. Please note that the LoA from Kenya does not display the complete name of the project activity. We understand that the clarification to this discrepancy has been noted in the Validation Report, version 3, page 6 and supporting documents. Please note that the Registry team has been informed accordingly of the above.
3.The DOE is requested to provide the geo-coordinates of the project site in the project view page, either by direct input or uploading a file containing the respective information.
The DOE is requested to include in the project view page the location details presented in Table 3 of the "Supporting project Information" of the PDD.
4.The DOE is requested to address the inconsistencies in the amount of emission reductions accordingly as per paragraph 7 (b) of EB 48, Annex 60.
PDD version 04.2 (12/02/2011), page 14, refers to the total estimated net anthropogenic GHG removals by sinks as 148,539 tCO2e. However, "Appendix 3 - No.2 TARASM_PDD4_Kibaranyeki", Worksheets "CERs" and ''Aexa'' refer to the amount of 163,290 tCO2e. Kindly address this inconsistency.
1.The DOE is requested to upload the respective modalities of communication (MoC) to the project view page as requested by paragraphs 8 (e) and 10 (d) of EB 48 Annex 60.
The DOE and Project Participants are kindly requested to use the approved "Modalities of Communication" avoiding modifications to the document itself (e.g. copy and paste of sections of "primary signatory")
2.The DOE is requested to upload a valid letter of approval/authorization (LoA) from the host party to the project view page as requested by paragraphs 8 (c) and (d) and 10 (c) of EB 48 Annex 60.
This is only a request for future submissions: The DOE and Project Participants are kindly requested to provide Letter of Approvals which fully display the project title of the project activity. Please note that the LoA from Kenya does not display the complete name of the project activity. We understand that the clarification to this discrepancy has been noted in the Validation Report, version 3, page 6 and supporting documents. Please note that the Registry team has been informed accordingly of the above.
3.The DOE is requested to provide the geo-coordinates of the project site in the project view page, either by direct input or uploading a file containing the respective information.
The DOE is requested to include in the project view page the location details presented in Table 3 of the "Supporting project Information" of the PDD.
4.The DOE is requested to address the inconsistencies in the amount of emission reductions accordingly as per paragraph 7 (b) of EB 48, Annex 60.
PDD version 04.2 (12/02/2011), page 14, refers to the total estimated net anthropogenic GHG removals by sinks as 148,539 tCO2e. However, "Appendix 3 - No.2 TARASM_PDD4_Kibaranyeki", Worksheets "CERs" and ''Aexa'' refer to the amount of 163,290 tCO2e. Kindly address this inconsistency.