Completeness Check
Submission incomplete:
1.The DOE is requested to upload the respective validation report to the project view page as requested by paragraph 8 (b) of EB 48 Annex 60.
The information on the determination of baseline as appendices to the PDD was uploaded in place of the validation report.

2.The PP/DOE are requested to provide relevant information on the determination of baseline as appendices to the PDD as requested by paragraphs 8 (g) and 9 (b) of EB 48 Annex 60.
The information on the determination of baseline as appendices to the PDD was uploaded in place of the validation report.