Completeness Check
Submission incomplete:
1.
In line with para 141-147 and para 168-171 of the CDM project cycle procedure for proramme of activities, only changes to the PoA-DD can be submitted under the post-registration changes (PRC) track. Changes to component project activities shall be done via notification of changes as per section 6.3 of the PCP. Thus, the notification of change is not permissible with the request for issuance.

2.
There is an inconsistency in the reference of post-registration changes. The verification and certification report does not refer to the temporary deviation as mentioned in C.3.1 of the monitoring report. Kindly clarify.

3.
There is an inconsistency in the version of the CPA-DD for 9981-0002. The monitoring report refers to version 2.1 (page 4) whereas the verification and certification report refers to version 9 dated 24/09/2018 (pages 3,18 and 20). Kindly clarify.