This a follow up on your request dated 24 April, 2014 to remove the resubmission for the monitoring period 01 Jan 2007 to 30 Sep 2008 for project "Hapugastenne and Hulu Ganga Small Hydropower Projects."

----
From: "OSL, Climate Change"
To: CDM Issuance of CERs
Date: 24/04/2014 09:01
Subject: RE: Request for issuance related to 00000085 - Resubmission confirmation

Dear CDM team,

We were not able to remove the post registration change for the resubmission of the issuance request for project activity 0085 (monitoring period 01 Jan 2007 to 30 Sep 2008). The button "Remove post-registration changes" did not work. In order to re-submit the issuance request, we thus uploaded again the PRC documents that were already submitted for prior approval on 2 December 2013 and approved on 18 March 2014.

Kindly remove the PRC documents submitted now again with the re-submission of the issuance request.
Best regards,
Michael Lehmann