Completeness Check
Submission incomplete:
1.Scope: The types of post registration changes are not consistent among the submitted documents.
Issue: 1. The requet for issuance form does not refer to a Post registraion change.
2. The verificatin/certification report refers to correction and changes to the project design, however, the view page, assessment opinion and the post registration change request form refer to temporaty deviation and correction.

2.Scope: A monitoring report using the form and guidelines for completing the monitoring report form (CDM-MR-FORM) has not been submitted with a request for issuance as required in the completeness check checklist for requests for issuance in line with PCP version 9 para 222.


3.Scope: The cross-referencing and versioning within and between the document are not correct and accurate.
Issue: The verification/certification report refer to the monitoring report version 4 dated 14.01.2016 however, no monitoring report has been submitted.