21:58 22 Nov 24
Completeness Check
Submission incomplete:
Scope: Cross-referencing and versioning within and between the document is not correct and accurate.
Issue: The Verification report refers to the revised Project Design Document for CDM project: “Nueva Aldea Biomass Power Plant Phase 2” version 4, dated 2013-08-06. However, the latest registered/ approved PDD is version 3, dated 2006-01-05.
Scope: Cross-referencing and versioning within and between the document is not correct and accurate.
Issue: The Verification report refers to the revised Project Design Document for CDM project: “Nueva Aldea Biomass Power Plant Phase 2” version 4, dated 2013-08-06. However, the latest registered/ approved PDD is version 3, dated 2006-01-05.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: