10:29 03 Oct 26
Completeness Check
Submission incomplete:
1.Scope: According to EB48 Annex 68 paragraph 8(a) a monitoring report must be submitted with a request for issuance.
Issue: Appendix B of the monitoring report does not include monitoring data from 1st of December 2009.
2.Scope: According to EB48 Annex 68 paragraph 8(b) a spreadsheet containing emission reduction calculation must be submitted with a request for issuance.
Issue: The spreadsheet does not include monitoring data from 1st of December 2009. Also in the spreadsheet "% error main & check meter" dates are not correct (March 2008-November 2008).
3.Scope: According to EB48 Annex 68 paragraph 9(e), cross-referencing and versioning within and between the document must be correct and accurate.
Issue:Verification report refers to monitoring report version 3 dated 26.08.2011 on page 2 where as the submitted monitoring report is version 4 dated 23.11.2011.
1.Scope: According to EB48 Annex 68 paragraph 8(a) a monitoring report must be submitted with a request for issuance.
Issue: Appendix B of the monitoring report does not include monitoring data from 1st of December 2009.
2.Scope: According to EB48 Annex 68 paragraph 8(b) a spreadsheet containing emission reduction calculation must be submitted with a request for issuance.
Issue: The spreadsheet does not include monitoring data from 1st of December 2009. Also in the spreadsheet "% error main & check meter" dates are not correct (March 2008-November 2008).
3.Scope: According to EB48 Annex 68 paragraph 9(e), cross-referencing and versioning within and between the document must be correct and accurate.
Issue:Verification report refers to monitoring report version 3 dated 26.08.2011 on page 2 where as the submitted monitoring report is version 4 dated 23.11.2011.

Offset now: visit the United Nations Carbon Offset Platform
Connect with us: