20:31 18 May 25
Completeness Check
Submission incomplete:
1.
The monitoring repot and verification/certification report refer to a temporary deviation. However, the issuance submission does not include a request for post-registration cases.
Temporarily deviation is a post-registration change and therefore documentation required for other type of post-registration change is also applicable for temporarily deviation. The only difference, as per para 128 of PCP-PA, version 2.0, is that for temporarily deviation the project participants are not required to prepare a revised PDD, but shall describe the proposed changes in the monitoring report.
2.Scope:
Issue: The verification and certification on page 5 refers to “Error! Reference source not found". Kindly clarify.
3.Scope: The cross-referencing and versioning within and between the document are not correct and accurate.
Issue: There is an inconsistency in the cross-referencing of the monitoring report version. The verification/certification report refers to monitoring report version 3 dated 09/12/2020 whereas the applicable monitoring report is version 2 dated 09/12/2020. Kindly clarify.
1.
The monitoring repot and verification/certification report refer to a temporary deviation. However, the issuance submission does not include a request for post-registration cases.
Temporarily deviation is a post-registration change and therefore documentation required for other type of post-registration change is also applicable for temporarily deviation. The only difference, as per para 128 of PCP-PA, version 2.0, is that for temporarily deviation the project participants are not required to prepare a revised PDD, but shall describe the proposed changes in the monitoring report.
2.Scope:
Issue: The verification and certification on page 5 refers to “Error! Reference source not found". Kindly clarify.
3.Scope: The cross-referencing and versioning within and between the document are not correct and accurate.
Issue: There is an inconsistency in the cross-referencing of the monitoring report version. The verification/certification report refers to monitoring report version 3 dated 09/12/2020 whereas the applicable monitoring report is version 2 dated 09/12/2020. Kindly clarify.
Offset now: visit the United Nations Carbon Offset Platform