22.3 MW Bundled grid connected Wind Power based electricity generation project in Gujarat.
[]
Host party(ies) India
Methodology(ies) ACM0002 ver. 5
Standardised Baselines N/A
Estimated annual reductions* 36,059
Start date of first crediting period. 17 Nov 04
Length of first crediting period. 10 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 14 Mar 06 - 12 Apr 06
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (2496 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Comment (92 KB) Submitted by:


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs