10 MW Solar Photovoltaic Power Plant in Rajkot, Gujarat (India)
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 16,994
Start date of first crediting period. 01 Sep 12
Length of first crediting period. 10 years
DOE/AE SGS-UKL
Period for comments 10 Jul 12 - 08 Aug 12
PP(s) for which DOE have a contractual obligation Green Infra Solar Energy Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1570 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
•	Why this location has been chosen for this project?
•	Will this project have impact on temperature in surrounding area?
•	What would be impact of negative environmental conditions of area upon project? What would be alternatives in that case?
•	How many skilled/unskilled people from surrounding area will be employed at this project during commissioning and operation? 
•	List of stakeholders and minutes of stakeholder meeting is not attached with PDD.
•	What is Complaint redress mechanism of a company, in case of villagers want to complain about solar panels?


From
Mahesh Pandya
Environmental Engineer
Paryavaran mitra
502, Raj Avenue, Bhaikakanagar road
Thaltej, Ahmedabad – 380059 India
Telefax - 079-26851321/1801
Submitted by: paryavaranmitra

Gujarat forum on CDM respectfully submit the following comments on the Project Design Document (PDD) for 10 MW Solar Photovoltic Power Plant in Village Merayadar, District – Rajkot, Gujarat, India.

1. Employment Opportunity - How many skilled/unskilled people from surrounding area will be employed at this project during commissioning and operation?
2. Impact on Environment -      Will this project have impact on temperature in surrounding area? What would be impact of negative environmental conditions of area upon project? What would be alternatives in that case?
3. Local stakeholder consultation - List of stakeholders and minutes of stakeholder meeting is not attached with PDD.
4. Compliant redress mechanism - What is Complaint redress mechanism of a company, in case of villagers want to complain about solar panels?

Falguni Joshi 
Gujarat forum On CDM (Email – gujaratforumoncdm@gmail.com) 
(Gujarat Forum on CDM – is a network of Individuals & Organisations working on Environmental issue & Monitoring of CDM projects in Gujarat, India.)
Submitted by: Gujarat Forum on CDM


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs