Project: 4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW - Crediting Period Renewal Request
Project 4118: Asahan 1 Hydroelectric Power Plant 2 x 90 MW

- project design document (1157 KB)

PDD appendices
Appendix 1 - RCP 4118 ER sheet (14 KB)
Appendix 2 - RCP 4118 CDM-RCPV-FORM_TC (525 KB)

- crediting period renewal form (110 KB)
Methodologies Used ACM0002 ver. 17 - Grid-connected electricity generation from renewable sources
Requests for post-registration changes PRC-4118-004
VVS Version VVS-PA 1.0
Standardized baselines used N/A
Amount of Reductions 1,021,075 metric tonnes CO2 equivalent per annum
Validation Opinion Validation opinion (466 KB)
Renewal Date 12 Jul 18   (view history)   completeness check: complete info & rep check: concluded
Crediting Period (requested for renewal) 01 Mar 18 - 28 Feb 25

Other crediting period(s): 01 Mar 11 - 28 Feb 18
Requests for Issuance
and related documentation