Project: 0772 Waste Heat based 10 MW captive power project “GPIL- WHRB 2” CDM PROJECT ACTIVITY - Request for post-registration changes
Project 0772 Waste Heat based 10 MW captive power project “GPIL- WHRB 2” CDM PROJECT ACTIVITY
PRC ref PRC-0772-001
Process track Issuance
DOE KBS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 18 Feb 07 - 17 Feb 17
Assessment opinion Assessment opinion (558 KB)
Revised PDD Revised PDD (555 KB)   Revised PDD - track changes (566 KB)
Supplementary documents Appendix 1 - Investment Analysis Sheet_revised.xls (230 KB)
Appendix 2 - Levelized Cost Sheet.xlsx (9640 bytes)
Appendix 3 - PLF Calculation Sheet.xlsx (11 KB)
Appendix 4 - ER Estimation sheet_revised.xls (27 KB)
Appendix 5 - DoE Response to UNCCC Clarification.pdf (41 KB)
Appendix 6 - PLF & CUF Calculation Sheet.xlsx (16 KB)
Signed form Signed form (320 KB)
DOE clarification
VVS version VVS 2.0
Current status 19 Dec 14 - Approved
Effective approval date: 19 Dec 14
Historic statuses 20 Nov 14 - Request published