Project: 1554 Ratchaburi Farms Biogas Project at Veerachai Farm - Request for post-registration changes
Project 1554 Ratchaburi Farms Biogas Project at Veerachai Farm
PRC ref PRC-1554-002
Process track Issuance
DOE SIRIM
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Apr 2011 - 30 Oct 2015
Assessment opinion Assessment opinion (146 KB)
Revised PDD  
Supplementary documents
Signed form Signed form (1036 KB)
DOE clarification
VVS version VVS 2.0
Current status 05 Feb 16 - Approved
Effective approval date: 05 Feb 16
Historic statuses 07 Jan 16 - Request published