Project: 4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW - Request for post-registration changes
Project 4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW
PRC ref PRC-4118-003
Process track Issuance
DOE ERM CVS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Jun 2012 - 01 Apr 2015
Assessment opinion Assessment opinion (99 KB)
Revised PDD  
Supplementary documents
Signed form Signed form (223 KB)
DOE clarification
VVS version VVS 2.0
Current status 21 Apr 17 - Approved
Effective approval date: 21 Apr 17
Historic statuses 23 Mar 17 - Request published