Review Request Form
Submitted Request for Review Form (Version 03.0)
SECTION 1: GENERAL INFORMATION
Title and UNFCCC reference number
of the project activity or
programme of activities (PoA)
0312: "18 MW Kemphole Mini Hydel Scheme (KMHS), by International Power Corporation Limited, India"
SECTION 2: BASIS FOR REVIEW REQUEST
Please indicate the relevant requirement(s) for which you have reasonable concern about whether the project activity or PoA complies,
by checking the appropriate box and specifying the relevant requirement(s) in the list below.

SECTION 3: COMMENTS SUPPORTING REVIEW REQUEST
Please elaborate the reason for requesting a review on the issues you indicated in section 2 above

The project participants have chosen option I under paragraph 72(a) of the Tool to calculate emission factor for an electricity system (version 07.0) to calculate the Build Margin emission factor for the project activity. As per this option of the Tool, for the third crediting period, the Built Margin emission factor calculated for the second crediting period should be used. However, it is observed that for the third crediting period, the Build Margin Emission Factor has been updated based on the most recent information, i.e. CEA CO2 Baseline Database version 15. The DOE is requested to clarify how it has validated the correctness of the application of the Tool to calculate the build margin emission factor for an electricity system (version 07.0).