KRSJ Bundled wind project in Tamil Nadu
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 29,597
Start date of first crediting period. 01 Apr 11
Length of first crediting period. 10 years
DOE/AE PJR CDM
Period for comments 05 Aug 10 - 03 Sep 10
PP(s) for which DOE have a contractual obligation KRSJ Emission Management Private Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (606 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Comment (64 KB) Submitted by: Kranti Kumar

1. Since most of the projects mentioned in the PDD have already been comissioned and are operational, have the project owners earned any revennue from VERs? If yes then has the same been considered in the IRR?

2. Why the deb-equity ratios for each project not been provided in the PDD?

3. Has the PO considered the incentives on account of Indirect tax like Concessional rates of Excide duty, Customs duty and lower VAT?

4) “As per MNRE, accelerated depreciation on WEG is permissible upto 80 % for Income tax calculation, subject to a minimum utilization for 6 mths in the year in which the reduction is claimed” have the project owners considered accelerated depreciation benefits?
Submitted by: Sandy


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs