Project: 9964 5 MW Solar PV Power Project at NTPC Faridabad - Issuance Request
Project 9964: 5 MW Solar PV Power Project at NTPC Faridabad
 
ISSUANCE STATUS Issued (on 07 Sep 18)   completeness check | info & rep check: concluded
Monitoring period 01 Jun 14 - 31 Aug 17
Monitoring report Monitoring report (249 KB)
Requests for post-registration changes submitted with the issuance request PRC-9964-001
 
Request for issuance Signed form (22 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 21,011
Serial Range: Block start: IN-5-249642331-2-2-0-9964     Block end: IN-5-249663341-2-2-0-9964
Verification and certification reports VVS/VVM version: VVS-PA 1.0
Certification report (167 KB)
Verification report (167 KB)
Additional documents Untitled (uploaded 12 Jul 18 11:05:40) (793 KB)
Untitled (uploaded 12 Jul 18 11:05:40) (19 KB)

Previous submissions

Submission date Outcome
17 May 18 CC complete | I&R incomplete