01:25 18 Sep 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3890 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Fuel switch from fossil fuel to biomass residues for cogeneration in integrated pulp and paper unit of ITC PSPD at Bhadrachalam |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to substantiate how it has validated the prior consideration of CDM, in particular to justify the CDM to be the decisive factor to the investment decision. In doing so, please refer to VVM version 1.2 paragraph 102 (a). 2. The DOE is requested to further explain how it has validated the levelized cost of the project activity and the baseline; in particular: (a) the equation used and the suitability of each parameters applied to the equation, in doing so, please refer to VVM version 1.2 paragraph 111; (b) the biomass price for each type of biomass and the weight ratio of biomass consumed, the overall biomass NCV, the ratio of the wood bark and the other biomass used in the calculation of the overall NCV, discount rate and the capital recovery factor, in doing so, please refer to VVM version 1.2 paragraph 111; and (c) the depreciation and the tax saving by depreciation, and the residual value. In doing so, please refer to EB 51 Annex 38 paragraph 5. 3. The DOE is requested to further substantiate the suitability of the biomass price and the investment cost for the project activity and the baseline on the basis of its specific local and sectoral expertise. In doing so, please refer to VVM version 1.2 paragraph 113 (c). 4. The DOE is requested to clarify the project description, in particular, how it has validated the increase in the on-site steam demand. In doing so, please refer to VVM version 1.2 paragraph 59. 5. The PP/DOE are requested to provide a transparent ex-ante calculation of project, baseline and leakage emissions expected during the crediting period by applying all relevant equations and by documenting how each equation is applied as required by "Guidelines for completing the simplified project design document and the form for proposed new small scale methodologies (CDM-SSC-NM) version 5" page 11 and VVM, version 1.2, paragraphs 18.c, 89-92. |
|
Date | 09 May 11 |