01:21 25 Apr 24
Project:
9610 5MW Solar PV Power Plant by AEPL
- Issuance Request
Project | 9610: 5MW Solar PV Power Plant by AEPL |
---|---|
ISSUANCE STATUS | Issued (on 09 Oct 19) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Feb 16 - 01 Apr 19 |
Monitoring report | Monitoring report (92 KB) |
Request for issuance | Signed form (52 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
26,865
Serial Range:
Block start: IN-5-255394725-2-2-0-9610
Block end: IN-5-255421589-2-2-0-9610
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (204 KB) Verification report (204 KB) |
Additional documents |
Untitled (uploaded 06 Jun 19 14:19:58) (2187 KB)
Untitled (uploaded 06 Jun 19 14:19:58) (19 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: