PoA monitoring report

Monitoring report data

Programme of Activities 00010004: City of Cape Town Landfill Gas Extraction and Utilisation Programme
PoA period 16 Sep 2014 - 15 Sep 2021
Coordinating/Managing Entity City of Cape Town
Host Party(ies) South Africa
Sectoral scopes 13 : Waste handling and disposal
Methodology Used ACM0001 ver. 15 - Flaring or use of landfill gas
Standardized baselines used ASB0001 ver 01.0 - Standardized baseline: Grid emission factor for the Southern African power pool
Submitting DOE TÜV NORD CERT GmbH
Monitoring period start (YYYY/MM/DD) 2014/10/01
Monitoring period end (YYYY/MM/DD) 2019/07/31
Version of the PoA DD applicable to this monitoring report 17
Version of the monitoring report 1
Monitoring report 2019-09-25 CDM MR Coastal Park V3.pdf (2603 KB)
Monitoring report number 10004-MP1-MRP1
Please tick the checkbox if this monitoring report relates to a straddling monitoring period, i.e. one that begins in 2020 and ends in 2021. In such case, the monitoring results from 1 Jan 2021 will be processed as per the EB 108 temporary measures.

Please proceed to split the straddling monitoring period into two parts, whereby one is ending on 31 Dec 2020 and a second – beginning on 1 Jan 2021. Please upload the same monitoring report version to each of the two parts of the straddling monitoring period.

At issuance, the system will require you to upload two separate issuance requests for each of the two parts of the straddling monitoring period. You will have to upload the same version of certification/verification report to each of the "related" issuance requests.
No The DOE confirms that the first part of the straddling monitoring period ends on 31 Dec 2020 and that the second part - begins on 1 January 2021. The DOE shall create the first and the second part of the straddling monitoring period and upload the same monitoring report to each part back-to-back (so that both submissions are received by the secretariat at the same time).