Project title of the project activity or programme of activities (PoA) for which issuance is requestedPower Generation using Waste pressure Energy of BF gas from Gas Expansion Turbine Station of BF-3 of Rashtriya Ispat Nigam Limited (9613)
DOE that requested for issuance and date of requestKBS (25 Mar 19)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1) As per page 12 of “Tool to calculate baseline, project and/or leakage emissions from electricity consumption”, version 01, default value of 3% for parameter TDLj,y can be used for project electricity consumption if the electricity consumption by all project and leakage electricity consumption sources is smaller than the electricity consumption of all baseline electricity consumption sources. Or else default value of 20% can be used. The DOE is requested to substantiate how it verified the use of default value of 3% is appropriate, in particular how it concluded that electricity consumption by all project and leakage electricity consumption sources is smaller than the electricity consumption of all baseline electricity consumption sources, considering that the electricity consumption of 135 MWh was the auxiliary electricity consumption from the project activity and such consumption would not have occurred in the baseline scenario. Please refer to paragraph 373(e) of VVS for project activities (version 02.0)..
Date 19 Jul 19