Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedBiomass based power project of VPL (10233)
DOE that requested for issuance and date of requestKBS (01 Mar 17)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence, Malfeasance
Please indicate reasons for the request for review
1) The DOE shall substantiate how it has verified that the project plant has been operated as per the description in the PDD for design capacity, since it is noticed that the actual gross power generation in 2016 (85016 MWh) indicates an average monthly capacity of 11.93 MW (i.e. based on the same method and assumptions at the time of registration, operational time of 330 days and 24 hours per day, PLF of 90%). Please refer to VVS version 09, paragraph 383(a).

2) The DOE shall also clarify how it has assessed FAR #09 from the validation report, which specifies that the verification DOE needs to check that the monthly generation should not breach the value of 10 MW @ 90% PLF. Please refer to VVS version 09, paragraph 409(g).
Date 23 Jun 17