Afforestation of Degraded Shengle Ecological Zone in Helinge'er of Inner Mongolia, China
[]
Host party(ies) China
Methodology(ies) AR-ACM0001 ver. 5
Standardised Baselines N/A
Estimated annual reductions* 7,195
Start date of first crediting period. 20 Jul 11
Length of first crediting period. 30 years
DOE/AE JACO
Period for comments 02 Oct 12 - 15 Nov 12
PP(s) for which DOE have a contractual obligation Hesheng Forest Silviculture Co. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (2657 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs