CECEP Dongtai Solar Power Generation Co., Ltd 1st and 2nd Stage Bundled PV Tidal Flat Ground Power Projects
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 58,982
Start date of first crediting period. 01 Aug 12
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 27 Apr 12 - 26 May 12
PP(s) for which DOE have a contractual obligation CECEP Dongtai Solar Power Generation Co., Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1150 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs