AWMS Methane capture and electricity generation project in PROAN farms, Jalisco
[]
Host party(ies) Mexico
Methodology(ies) ACM0010 ver. 5
Standardised Baselines N/A
Estimated annual reductions* 214,368
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 10 years
DOE/AE TUEV-RHEIN
Period for comments 25 Dec 10 - 23 Jan 11
PP(s) for which DOE have a contractual obligation Proteina Animal S.A. de C.V. (PROAN)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1244 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs