Nam Mang 1 Hydropower Project
[]
Host party(ies) Lao People's Democratic Republic
Methodology(ies) ACM0002 ver. 17
Standardised Baselines N/A
Estimated annual reductions* 125,776
Proposed start date of PA 15 Apr 13
Start date of first crediting period. 01 Jan 17
Length of first crediting period. 7 years
DOE/AE CTI Certification Co., Ltd.
Period for comments 01 Oct 16 - 30 Oct 16 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation Nam Mang 1 Power Co., Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (700 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs