40 MW Wind Power Project at Maliya, Gujarat
[]
Host party(ies) India
Methodology(ies) ACM0002 ver. 17
Standardised Baselines N/A
Estimated annual reductions* 117,849
Proposed start date of PA 28 Jul 16
Start date of first crediting period. 01 May 17
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 03 Mar 17 - 01 Apr 17 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation Orange Agar Wind Power Pvt. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1110 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs