BRT Metrobus Insurgentes and Eje 4, Mexico
[]
Host party(ies) Mexico
Methodology(ies) ACM0016
Standardised Baselines N/A
Estimated annual reductions* 70,303
Start date of first crediting period. 01 Jan 11
Length of first crediting period. 7 years
DOE/AE AENOR INTERNACIONAL, S.A.U.
Period for comments 05 May 10 - 03 Jun 10
PP(s) for which DOE have a contractual obligation International Bank for Reconstruction and Development (IBRD)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (2466 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs