South Isfahan Power Plant
[]
Host party(ies) Iran (Islamic Republic of)
Methodology(ies) ACM0007 ver. 6
Standardised Baselines N/A
Estimated annual reductions* 970,895
Start date of first crediting period. 23 Sep 13
Length of first crediting period. 10 years
DOE/AE SIRIM
Period for comments 07 Sep 12 - 06 Oct 12
PP(s) for which DOE have a contractual obligation South Isfahan Power Plant FZ Co.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (725 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs