UTE 10 MW Grid Connected Wind Power Farm at Caracoles Hill
[]
Host party(ies) Uruguay
Methodology(ies) AMS-I.D. ver. 15
Standardised Baselines N/A
Estimated annual reductions* 25,554
Start date of first crediting period. 05 Jan 10
Length of first crediting period. 7 years
DOE/AE AENOR INTERNACIONAL, S.A.U.
Period for comments 19 Feb 10 - 20 Mar 10
PP(s) for which DOE have a contractual obligation International Bank for Reconstruction and Development (IBRD) as the Trustee of the Spanish Carbon Fund
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (342 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.