05:27 25 May 12
Project:
0819 Zhongjieneng Suqian 2*12MW Biomass Direct Burning Power Plant Project
- Issuance Request
| Project | 0819: Zhongjieneng Suqian 2*12MW Biomass Direct Burning Power Plant Project |
|---|---|
| ISSUANCE STATUS | Issued (on 09 Mar 12) completeness check: complete info & rep check: complete |
| Monitoring period | 01 Aug 10 - 31 Jul 11 |
| Monitoring report |
Monitoring report (234 KB)
|
| Request for issuance |
Signed form (286 KB)
|
| Amount of CERs |
125,382
Serial Range:
Block start: CN-5-527105791-1-1-0-819
Block end: CN-5-527231172-1-1-0-819
|
| Verification and certification reports |
Certification report (2651 KB)
Verification report (2651 KB)
|
| Additional documents |
Suqian 5th ER.zip (17 KB)
MR version 1.2.pdf (237 KB)
|
Previous submissions
| Submission date | Outcome |
|---|---|
| 29 Sep 11 | CC complete | I&R incomplete |

Monitoring report
Suqian 5th ER.zip