Project: 4882 Guohua Rongcheng Phase II Wind Farm Project - Issuance Request
Project 4882: Guohua Rongcheng Phase II Wind Farm Project
 
ISSUANCE STATUS Issued (on 05 Sep 14)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jun 12 - 31 Jan 14
Monitoring report Monitoring report (363 KB)
 
Request for issuance Signed form (513 KB)
Amount of CERs CERs issued up to 31 December 2012: 54,191
CERs issued from 01 Jan 2013 until 31 December 2020: 102,587
Total amount of CERs: 156,778
Serial Range: Block start: CN-5-890558388-1-1-0-4882     Block end: CN-5-890612578-1-1-0-4882
Serial Range: Block start: CN-5-890612579-2-2-0-4882     Block end: CN-5-890715165-2-2-0-4882
Verification and certification reports VVS/VVM version: VVS 5.0
Certification report (21 KB)
Verification report (373 KB)
Additional documents ER_Calculation_Rongcheng_II_Ref.4882-v2.xls (33 KB)
Revised_MR_Rongcheng_Phase_II-_v2.pdf (277 KB)