00:43 20 Apr 24
Project:
4287 Luogu 10MW Hydropower Station Project in Sichuan Province
- Issuance Request
Project | 4287: Luogu 10MW Hydropower Station Project in Sichuan Province |
---|---|
ISSUANCE STATUS | Issued (on 03 Dec 15) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 25 May 15 |
Monitoring report | Monitoring report (417 KB) |
Request for issuance | Signed form (72 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
84,081
Serial Range:
Block start: CN-5-956656496-2-2-0-4287
Block end: CN-5-956740576-2-2-0-4287
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (84 KB) Verification report (84 KB) |
Additional documents |
revised montoring report (417 KB)
ER calculation (40 KB) document list (93 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: