Project: 2624 Baoshan Supahe Chaoyang Hydropower Station - Crediting Period Renewal Request
[]
Project 2624: Baoshan Supahe Chaoyang Hydropower Station

- project design document (2467 KB)

PDD appendices
Appendix 1 - CSPG EF and Chaoyang ER calculation sheet (202 KB)
Appendix 2 - List of documents submitted_Chaoyang (35 KB)

- crediting period renewal form (35 KB)
Methodologies Used ACM0002 ver. 17 - Grid-connected electricity generation from renewable sources
VVS Version VVS 9.0
Standardized baselines used N/A
Amount of Reductions 79,174 metric tonnes CO2 equivalent per annum
Validation Opinion Validation opinion (190 KB)
Renewal Date 19 May 17 (Renewable)   (view history)   completeness check: complete info & rep check: concluded
Crediting Period (requested for renewal) 09 Oct 16 - 08 Oct 23

Other crediting period(s): 09 Oct 09 - 08 Oct 16
Requests for Issuance
and related documentation