14:34 18 Apr 24
Project:
6229 Luoyang Zhangluoping MSW Landfill Site LFG Recovery to Power Project
- Issuance Request
Project | 6229: Luoyang Zhangluoping MSW Landfill Site LFG Recovery to Power Project |
---|---|
ISSUANCE STATUS | Issued (on 25 Oct 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 29 Feb 16 |
Monitoring report | Monitoring report (293 KB) |
Request for issuance | Signed form (1100 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
111,483
Serial Range:
Block start: CN-5-998260980-2-2-0-6229
Block end: CN-5-998372462-2-2-0-6229
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (898 KB) Verification report (971 KB) |
Additional documents |
ER calculation spreadsheet_Zhangluoping MSW_1st (81 KB)
MR(V2)_Zhangluoping MSW_1st (429 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: