Project: 5770 Buseruka Mini Hydro Power Plant - Issuance Request
Project 5770: Buseruka Mini Hydro Power Plant
 
ISSUANCE STATUS Issued (on 19 May 16)   completeness check: complete | info & rep check: concluded
Monitoring period 21 May 12 - 31 Jan 15
Monitoring report Monitoring report (441 KB)
 
Request for issuance Signed form (2664 KB)
Amount of CERs CERs issued up to 31 December 2012: 189
CERs issued from 01 Jan 2013 until 31 December 2020: 28,087
Total amount of CERs: 28,276
Serial Range: Block start: UG-5-1676490-1-1-0-5770     Block end: UG-5-1676678-1-1-0-5770
Serial Range: Block start: UG-5-1676679-2-2-0-5770     Block end: UG-5-1704765-2-2-0-5770
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (885 KB)
Verification report (885 KB)
Additional documents 5770 1 Monitoring Report (713 KB)
5770 1 CER Calculation (66 KB)