00:58 24 Apr 24
Project:
4730 Keyouzhongqi Shenneng Hangali Wind Farm Project
- Issuance Request
Project | 4730: Keyouzhongqi Shenneng Hangali Wind Farm Project |
---|---|
ISSUANCE STATUS | Issued (on 31 Oct 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 30 Jun 12 - 29 Feb 16 |
Monitoring report | Monitoring report (451 KB) |
Request for issuance | Signed form (108 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
666
CERs issued from 01 Jan 2013 until 31 December 2020: 376,116 Total amount of CERs: 376,782
Serial Range:
Block start: CN-5-999151945-1-1-0-4730
Block end: CN-5-999152610-1-1-0-4730
Serial Range: Block start: CN-5-999152611-2-2-0-4730 Block end: CN-5-999528726-2-2-0-4730 |
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (545 KB) Verification report (545 KB) |
Additional documents |
4730// ER (61 KB)
4730// MR (917 KB) |
Offset now: visit the United Nations Carbon Offset Platform