15:10 24 May 12
Project:
2106 Yunnan Lianghe Hulukou Hydropower Station
- Issuance Request
| Project | 2106: Yunnan Lianghe Hulukou Hydropower Station |
|---|---|
| ISSUANCE STATUS | Issued (on 01 Mar 12) completeness check: complete info & rep check: complete |
| Monitoring period | 27 Jun 10 - 10 Aug 11 |
| Monitoring report |
Monitoring report (449 KB)
|
| Request for issuance |
Signed form (120 KB)
|
| Amount of CERs |
93,989
Serial Range:
Block start: CN-5-525161333-1-1-0-2106
Block end: CN-5-525255321-1-1-0-2106
|
| Verification and certification reports |
Certification report (42 KB)
Verification report (343 KB)
|
| Additional documents |
MR (Ver. 02) (436 KB)
ER sheet (38 KB)
|

Monitoring report
ER sheet