12:37 29 Mar 24
Project:
2098 The 84 MW New Bong Escape Hydropower Project, Azad Jammu and Kashmir (AJK), Pakistan
- Issuance Request
Project | 2098: The 84 MW New Bong Escape Hydropower Project, Azad Jammu and Kashmir (AJK), Pakistan |
---|---|
ISSUANCE STATUS | Issued (on 27 Apr 17) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Oct 14 - 30 Sep 15 |
Monitoring report | Monitoring report (1021 KB) |
Request for issuance | Signed form (174 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
251,178
Serial Range:
Block start: PK-5-7118786-2-2-0-2098
Block end: PK-5-7369963-2-2-0-2098
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (570 KB) Verification report (636 KB) |
Additional documents |
ER calculation spreadsheet_New Bong Escape Hydropower Project_3rd (58 KB)
MR(V2)_New Bong Escape Hydropower Project_3rd (620 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: