Project: 1177 Fujian Pingtan Changjiang’ao 100 MW Wind Power Project - Issuance Request
Project 1177: Fujian Pingtan Changjiang’ao 100 MW Wind Power Project
 
ISSUANCE STATUS Withdrawn (on 08 Apr 09)  
Monitoring period 19 Dec 07 - 27 Jun 08
Monitoring report Monitoring report (136 KB)
  Note:
Issuance request(s) for this monitoring period have been re-submitted:
- Status: Issued (Request for review period: 06 May 10 - 20 May 10)
 
Request for issuance Signed form (674 KB)
Amount of CERs 137,810
Verification and certification reports Certification report (55 KB)
Verification report (527 KB)
Additional documents Monitoring Report (243 KB)
Request for review Request 1
Request 2
Request 3


EB meeting: EB46
(at which the Board considers the request(s) for review, decides whether to undertake the review and, if so, determine its scope and selects a review team)

Initial comments:
DOE & PP - Initial comments (n/a)