13:59 20 Apr 24
Project:
0258 Nueva Aldea Biomass Power Plant Phase 1
- Issuance Request
Project | 0258: Nueva Aldea Biomass Power Plant Phase 1 |
---|---|
ISSUANCE STATUS | Issued (on 27 Aug 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 11 - 31 Dec 11 |
Monitoring report | Monitoring report (1933 KB) |
Request for issuance | Signed form (64 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
193,653
Serial Range:
Block start: CL-5-18993632-1-1-0-258
Block end: CL-5-19187284-1-1-0-258
|
Verification and certification reports |
VVS/VVM version:
VVS 6.0
Certification report (5936 KB) Verification report (5936 KB) |
Additional documents |
4.7 Monrep NAF1 CP1 MP6 140505 ver7 (1788 KB)
5.1.f NA F1 monit CP1 MP6 140505 ver5 (48 KB) 7.1.d Emission_Factor_SIC_2011_ACM0002_Ver_04_ver0.4 (Tabla_MR (1134 KB) |
Offset now: visit the United Nations Carbon Offset Platform