09:10 25 Apr 24
Project:
9305 Hanergy Pizhou Solar PV Power Co., Ltd 30MW PV Power Station Project
- Issuance Request
Project | 9305: Hanergy Pizhou Solar PV Power Co., Ltd 30MW PV Power Station Project |
---|---|
ISSUANCE STATUS | Issued (on 17 Nov 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 29 Feb 16 |
Monitoring report | Monitoring report (503 KB) |
Request for issuance | Signed form (190 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
92,940
Serial Range:
Block start: CN-5-1004067724-2-2-0-9305
Block end: CN-5-1004160663-2-2-0-9305
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (687 KB) Verification report (769 KB) |
Additional documents |
ER calculation spreadsheet_Hanergy Pizhou_1st (58 KB)
MR(V02)_Hanergy Pizhou_1st (558 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: