Project: 9305 Hanergy Pizhou Solar PV Power Co., Ltd 30MW PV Power Station Project - Issuance Request
Project 9305: Hanergy Pizhou Solar PV Power Co., Ltd 30MW PV Power Station Project
 
ISSUANCE STATUS Issued (on 17 Nov 16)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 13 - 29 Feb 16
Monitoring report Monitoring report (503 KB)
 
Request for issuance Signed form (190 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 92,940
Serial Range: Block start: CN-5-1004067724-2-2-0-9305     Block end: CN-5-1004160663-2-2-0-9305
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (687 KB)
Verification report (769 KB)
Additional documents ER calculation spreadsheet_Hanergy Pizhou_1st (58 KB)
MR(V02)_Hanergy Pizhou_1st (558 KB)