Project: 3008 Nanjing Jinling Grid Connected Natural Gas Combined Cycle Power Plant Project - Issuance Request
Project 3008: Nanjing Jinling Grid Connected Natural Gas Combined Cycle Power Plant Project
 
ISSUANCE STATUS Issued (on 30 Sep 15)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 13 - 30 Apr 15
Monitoring report Monitoring report (766 KB)
 
Request for issuance Signed form (2654 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 1,411,805
Serial Range: Block start: CN-5-946866274-2-2-0-3008     Block end: CN-5-948278078-2-2-0-3008
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (1387 KB)
Verification report (1387 KB)
Additional documents 3008 7 Monitoring Report (817 KB)
3008 7 CER Calculation (131 KB)

Previous submissions

Submission date Outcome
11 Aug 15 CC incomplete